Reedy River Basin Sewer Tunnel
Location: Greenville, South CarolinaOwner: Renewable Water Resources (ReWA)Completed: June 2020 This project includes construction of 6,000 LF of 130” ID rock
Location: Greenville, South CarolinaOwner: Renewable Water Resources (ReWA)Completed: June 2020 This project includes construction of 6,000 LF of 130” ID rock
Location: St. Joseph, MOOwner: City of St. Joseph, MOCompleted: October 2019 The Blacksnake Creek Stormwater Separation Improvement Project
Location: Omaha, NEOwner: The City of Omaha, Public Works Dept.Completed: December 2017 This project includes 2,480 lf of
Location: City of Mississauga, CanadaOwner: Peel RegionCompleted: November 2017 This project included the construction of a curved microtunnel
Location: Barrie, Ontario, CanadaOwner: Ministry of TransportationCompleted: November 2017 CRS Tunnelling was elected as the Microtunnelling Sub-Contractor to
Location: Cleveland, OHOwner: Northeast Ohio Regional Sewer DistrictCompleted: October 2017 The Superior-Stones Levee CSO Improvement was part of a
Location: Omaha, NEOwner: City of Omaha, Public Works DeptartmentCompleted: October 2016 This project was created to provide additional
Location: Milwaukee, WIOwner: KM DevelopmentCompleted: July 2016 Anchored earth retention system providing a “belt and suspenders” approach to
Location: De Pere, WIOwner: Wisconsin DOTCompleted: July 2016 Installation of over 800 posts for noise wall project along
Location: Milwaukee, WIOwner: The Bradley CenterCompleted: July 2016 Large diameter design-build helicap piers for boardwalk at The Bradley
Location: Edmonton, AlbertaOwner: The City of EdmontonCompleted: June 2016 Dibco-CRS, A Joint Venture has been awarded a Design
Location: Mississauga, Ontario, CanadaOwner: Region of PeelCompleted: May 2016 In April 2015, CRS Tunnelling – Dibco Underground, JV
Location: Richmond Hill, Ontario, CanadaOwner: Region of YorkCompleted: February 2016 The primary scope of this subcontract included the construction
Location: Cleveland, OHOwner: Northeast Ohio Regional Sewer DistrictCompleted: December 2015 On October 3, 2013, the Northeast Ohio Regional
Location: Lorain, OHOwner: City of Lorain OhioCompleted: June 2015 On January 17th 2012, the Lorain City Council approved
Location: Green Bay, WIOwner: WI Department of TransportationCompleted: May 2015 In August 2013, Super Excavators was elected to
Location: Green Bay, WIOwner: WI Department of TransportationCompleted: May 2015 In August 2013, Super Excavators was elected to
Location: Town of Caledon – Toronto, CanadaOwner: Region of PeelCompleted: September 2014 On August 14, 2013, Dibco-CRS, A
Location: Green Bay, WIOwner: Green Bay PackersCompleted: March 2014 Tunnel construction in confined space under extreme conditions utilizing
Location: Green Bay, WIOwner: City of Green BayCompleted: March 2014 SX Foundations recently completed a subcontract for Miron
Location: Providence, RIOwner: Narragansett Bay Commission (NBC)Completed: March 2014 This project was located in Historic Providence, Rhode Island, and
Location: Logansport, INOwner: Logansport Municipal UtilitiesCompleted: December 2013 On December 12, 2012, Super Excavators was awarded the Logansport
Location: Milwaukee, WIOwner: Blue Ribbion Redevelopment Fund III, LLCCompleted: September 2013 SX Foundations, Inc. provided subcontracting services to
Location: Milwaukee, WIOwner: Great Lakes Acquisition Center (GLAC), Department of Veterans AffairsCompleted: June 2013 Project 695-12-118 – 115