Skip to content

University Relief Storm Sewer Project – Tunneling Complete

On July 30th, Super Excavators completed the tunneling portion of the University Relief Storm Sewer Project, in Madison, WI. Completion of the 96-inch diameter RCP storm sewer, and demobilization of the Lovat TBM is an important milestone for the project. The longest tunnel drive completed was 1,000 linear feet, and the ground conditions consisted of boulders and sands. To wrap up work on this project, our crews will begin work on sanitary sewer lines, structures, and road work. This project is on schedule for completion by the end of September, 2013.